The form was specific: individual tenant logins, configurable download limits and paid speed upgrades; NBN equipment in the basement comms room and each level's riser; racks, patch panels, managed switches, router and firewall, all equipment and cabling included; at least two ceiling access points per level.

- 1
Questions first
We replied quickly and asked for the address, floor plans, reflected ceiling plans, electrical and communications drawings, meeting room capacities, wall and fire door construction, the internet provider, maximum residents and devices, preferred plans and the construction programme.
- 2
Answered point by point
The builder answered each one and shared the full drawing set and specifications.


How the owner plans to run the building decides how the network is designed.
- 1
A base plan in the rent
25 Mbps down and 8 Mbps up for every tenant: enough for browsing, social media and video.
- 2
Paid upgrades, self-serve
Tenants can buy faster plans when they want them, such as 50 Mbps down / 17 up or 500 Mbps down / 42 up. The design links the login system to an external payment page, so speeds change automatically after payment, with no work for the manager.
- 3
A login per tenant
Up to 88 individual accounts, issued per unit or per person, with each plan's limit covering all of that tenant's devices.
- 4
Privacy between tenants
VLANs and client isolation, so tenants can't see each other's devices or reach the building's systems.
Solid-core fire doors, concrete slabs and the bathroom inside each unit all weaken the signal. With access points only in the corridors, bedrooms and desks by the windows would suffer.
The electrical drawings already show 46 access point locations: 8 on the ground floor, 11 on each of Levels 1 to 3 and 5 on Level 4. That's one in each of the 44 units plus the two meeting rooms, each served by a shielded Cat6A outlet. After checking them, we set three layouts side by side for the owner to choose by budget:
- 1
One per unit, 46 in all
Recommended. A low-power ceiling access point in every unit, clear of the fire doors and bathrooms. Each one serves one or two people, peak hours stay smooth, and a fault only affects one unit.
- 2
Shared by neighbours, about 26
Two units either side of a plasterboard wall share one access point, at lower cost.
- 3
Corridor access points, about 14
The cheapest, with weaker signal in the bedrooms. Unused locations keep a Cat6A outlet so access points can be added later.

Confirmed before ordering: final quantities are set once coverage is confirmed in detailed design, and no access points are ordered without the owner's written approval.
One main internet service and gateway for the whole building, in the basement comms room, with the NBN equipment on each level staying where the builder planned it.
- 1
Core rack
A 42RU rack in the basement comms room, with a UPS and surge protection.
- 2
Fibre backbone
Fibre from the comms room to a managed PoE switch in each level's riser, powering that level's access points.
- 3
Internet service
A business NBN plan with stronger upload to start, 1000/400 Mbps, upgradable to 2000/500 Mbps or enterprise fibre.
- 4
Provider permission
Sharing one service among many tenants is subject to the provider's terms, so we'll help the owner get written permission from the provider.


The builder wanted us to design the access point layout and set the locations and cabling up front, so they wouldn't carry coverage problems or extra cable runs from a weak layout later. They can also allow for extra provision points where we recommend them.

- 1
The builder's electrician
Cat6A cabling and the fibre backbone to our layout, cable certification, trays and fire sealing.
- 2
Us
Access point design, the comms rack and level enclosures, business network equipment, tenant login and billing setup, and final testing and handover.
- 3
Two budget packages
The electrical drawings already give some of the work to the electrician, so we split our budget into two packages and the client doesn't pay twice for the same work.
- 4
Timing
Cable and backbone go in before the ceilings are sheeted, and equipment is fitted afterwards.
Where it stands: the project is in progress, the building is under construction and the network will follow the build. The cover is an illustrative photo of an apartment building (Unsplash), not this project.